Pavement Repairs Updates

Pavement Repairs

Project Status - Construction in Progress

7/2/13, PARKING LOT N PAVEMENT REPAIR JULY 8 - 19, 2013
This Wednesday, July 3, Wildish Construction will mark off part of Parking Lot N, and on Monday, July 8, they will mobilize on site to repair pavement in the area. A barricade north of the smoking shelter will direct pedestrians into the path next to the pavement. ADA parking and pedestrian access will be maintained near Building 7. Truck lane access will also be maintained. Most of the heavy work is expected to be completed by July 19, but some additional small repairs and striping may continue. Please observe barricades and exercise caution in these work areas. For questions, please contact Russ Pierson at extension 5727 or Brian McMurray at extension 5829.

pavement repairs project area